ADU•November 20, 2026

The City of Temecula Permit Ready ADU Plans, Explained

Garage interior showing exposed beams and walls being prepared for ADU building

Updated November 11, 2026

For property-specific planning and project coordination, explore our construction services in Temecula.

By Spencer Woollard, Woollard Construction

Direct Answer

The Temecula PRADU program is the City of Temecula's Permit Ready Accessory Dwelling Unit program: five free, pre-designed detached ADU plan sets from 499 to 1,194 sq ft [1]. Downloading them costs nothing. Permit, plan check and school district fees still apply, and only the 499 sq ft Studio avoids both impact and school fees [2][6].

TL;DR

  • The City of Temecula publishes five Permit Ready ADU (PRADU) plans as free PDFs: Studio 499 sq ft, 1 Bedroom/1 Bathroom 625, 2 Bedroom/1 Bathroom 749, 2 Bedroom/2 Bathroom 909, 3 Bedroom/2 Bathroom 1,194 [1].
  • Free plans, not free permits. Building permit and plan check fees apply to every plan [1][2].
  • Only the 499 sq ft Studio is exempt from both development impact fees and TVUSD school fees. The 625 and 749 plans skip impact fees but owe school fees at $5.38 per sq ft. The 909 and 1,194 plans owe both [2][6].
  • From January 1, 2027, SB 1117 limits impact fees on the two larger plans to the square footage above 750 [8].
  • Permit Ready means the building is drawn and pre-reviewed. You still supply the site plan, Title 24 energy calcs, a WQMP packet and a soils report over 500 sq ft, and changing the plans voids the expedited path [2].
  • Plan review usually runs 7 to 10 business days after a 24 business hour completeness check, then clearances and fees before issuance [2].
  • Setbacks under 5 ft, septic, pools, fire access over 150 ft and HOA rules are the usual reasons a fixed plan does not fit [2].

One liner: Temecula's PRADU plans are free to download, but the plan size you pick, not the program, decides which fees you pay.

Key Numbers

StatWhat it measuresSource
5 plan sets499 to 1,194 sq ft, free PDFsCity of Temecula ADU page, 2026
749 sq ft or lessExempt from development impact feesCity handout CD-70; Gov Code 66311.5, 2023; 2026
500 sq ft or lessExempt from TVUSD school feesTVUSD, effective June 16, 2026, 2026
$5.38 per sq ftTVUSD rate on an ADU over 500 sq ftTVUSD, 2026
About $3,363 / $4,030 / $4,890 / $6,424Computed TVUSD fee at 625, 749, 909 and 1,194 sq ftTVUSD rate times plan size, 2026
159 and 444 sq ftImpact fee basis for the 909 and 1,194 plans from January 1, 2027SB 1117, 2026
7 to 10 business daysTypical PRADU plan reviewCity handout CD-70, 2023
24 business hoursSubmittal completeness checkCity handout CD-70, 2023
10 business daysLead time to request an ADU addressCity handout CD-70, 2023
4 ftMinimum side and rear setbackCity handout CD-70, 2023
1,200 sq ft or 50 percent of the main homeMaximum ADU size, whichever is lessCity PL-73 handout, 2026

The City of Temecula will hand you a full set of accessory dwelling unit (ADU) plans for nothing. Five of them, from a 499 sq ft studio to a 1,194 sq ft three bedroom, drawn and pre-reviewed by the city's own Building and Safety Division [1]. That is the Temecula PRADU program, and it is one of the better deals a Temecula homeowner can get on an ADU. It is also widely misunderstood. "Free plans" does not mean free permits, and "under 750 sq ft" does not mean fee free. Only one of the five plans clears every fee, and the plan you pick decides which bills show up before the city issues your permit.

What the Temecula PRADU program is

In short: Five city-drawn detached ADU plan sets, free to download, with permit and build fees still owed.

The Permit Ready Accessory Dwelling Unit (PRADU) program is a set of five pre-designed detached ADU plan sets that the City of Temecula publishes as PDFs on its ADU page [1]. Anyone can download them. The city's wording is exact: the plans are available for free, and there are fees for submitting and building your PRADU [1]. So these are the free ADU plans Temecula offers in the literal sense. The design work is done. Everything that depends on your lot, your utilities and your school district is not.

The city introduced the program in 2023. Staff ran a public workshop on February 22, 2023 to walk through the plans and the six step process [3], and the Permit Ready ADU Handout (form CD-70) that governs the program was last revised July 20, 2023 [2]. The handout is the document the city tells every property owner, contractor and design professional to read before starting a PRADU project [1].

Two points from that handout frame everything else. First, PRADUs take care of most of the design work, but the plans still have to be completed by the owner or a professional before submittal [2]. Second, a PRADU may not be feasible for every project. When it is not, the city says you may be eligible to submit plans for a custom ADU instead [2]. The program is a shortcut, not a guarantee.

The five Permit Ready ADU plans

In short: 499, 625, 749, 909 and 1,194 sq ft, with the two smallest sizes set one square foot under the 500 and 750 fee lines.

The city publishes five plan sets, each as its own PDF on the Temecula ADU page [1]. These are the only permit ready ADU plans Temecula homeowners can download, and they step up in size and bedroom count. Two size thresholds matter more than any floor plan detail: 500 sq ft and 750 sq ft. The next section explains why. For now, here is the lineup.

Plan (city label)Size (sq ft)Under 500 sq ft749 sq ft or less
Studio499YesYes
1 Bedroom/1 Bathroom625NoYes
2 Bedroom/1 Bathroom749NoYes
2 Bedroom/2 Bathroom909NoNo
3 Bedroom/2 Bathroom1,194NoNo

Plan names and sizes from the City of Temecula ADU page and the plan title sheets [1][10].

The sizes are not random. The 2 Bedroom/1 Bathroom plan stops at 749 sq ft, one square foot under the 750 sq ft line that state law uses for impact fees. The Studio stops at 499 sq ft, one foot under the 500 sq ft line the school district uses. The 2 Bedroom/2 Bathroom plan, at 909 sq ft, is 159 sq ft past the impact fee line, and the 3 Bedroom/2 Bathroom plan sits 6 sq ft under the city's 1,200 sq ft ceiling.

That ceiling comes from the city's general ADU rules, not the PRADU program. Temecula's ADU application handout caps a unit at 50 percent of the existing home's floor area or 1,200 sq ft, whichever is less, and sets a floor of 150 sq ft [4]. On a 1,600 sq ft house, the two larger plans are off the table before you open the PDF. Check that math before you fall for a floor plan.

Which fees each plan pays

In short: Only the Studio avoids both impact and school fees; 625 and 749 owe school fees; 909 and 1,194 owe both, with impact fees shrinking to the area above 750 sq ft from January 1, 2027.

Only one of the five plans, the 499 sq ft Studio, is exempt from both development impact fees and school fees. The 625 and 749 sq ft plans skip impact fees but still owe Temecula Valley Unified School District (TVUSD) fees, and the 909 and 1,194 sq ft plans owe both [2][6]. Every plan pays building permit and plan check fees [2]. The phrase you will see repeated online, that an ADU under 750 sq ft "pays no fees," is true of one fee and false of the rest.

Here is how it breaks down, plan by plan.

PlanSize (sq ft)Development impact fee, permits issued before Jan 1, 2027Development impact fee, from Jan 1, 2027TVUSD school fee at $5.38 per sq ftPermit and plan check fees
Studio499ExemptExempt$0 (500 sq ft or less, exemption application required)Yes
1 Bedroom/1 Bathroom625ExemptExemptAbout $3,363Yes
2 Bedroom/1 Bathroom749ExemptExemptAbout $4,030Yes
2 Bedroom/2 Bathroom909Prorated on all 909 sq ftProrated on 159 sq ftAbout $4,890Yes
3 Bedroom/2 Bathroom1,194Prorated on all 1,194 sq ftProrated on 444 sq ftAbout $6,424Yes

School fee figures are the district's published rate multiplied by plan size; the district states the final amount on its Certificate of Compliance [6]. Impact fee status from the city handout and Government Code 66311.5 [2][5].

Impact fees. The city's Permit Ready ADU Handout puts it plainly: development impact fees apply if the PRADU is larger than 749 sq ft, and at 749 sq ft or less the unit is exempt, though building permit fees still apply [2]. That mirrors state law. Government Code 66311.5 bars any impact fee on an ADU with 750 sq ft of interior livable space or less, and requires fees on larger units to be charged in proportion to the primary home's square footage [5]. Temecula ADU impact fees for a 909 sq ft unit behind a 1,800 sq ft house are therefore about half of what the city charges a new detached home, under the rule in force today.

The January 1, 2027 change. Senate Bill 1117, signed September 29, 2026, rewrites that proration for permits issued on or after January 1, 2027 [8]. For up to two ADUs on a lot, the proportional fee is calculated only on the square footage above 750 [5][8]. The 909 plan drops from a 909 sq ft basis to 159 sq ft. The 1,194 plan drops from 1,194 to 444. The three smaller plans were already exempt, so nothing changes for them. If you are choosing one of the two larger plans, ask the city which rule applies to an application still in review on January 1.

School fees. TVUSD developer fees run on a different line, 500 sq ft, and that line comes from the Education Code rather than the ADU statute [7][11]. The district's current schedule, effective June 16, 2026, charges $5.38 per sq ft on a detached or attached ADU over 500 sq ft and $0 on a unit of 500 sq ft or less, with an exemption application required for the smaller units [6]. The fee is assessed on the unit's assessable square footage [6]. The city will not issue your permit until you hand over the TVUSD clearance letter [2], which the district calls a Certificate of Compliance and issues whether or not a fee was due [6].

So the 749 plan is not a fee free plan. It is an impact fee free plan with roughly $4,030 in school fees attached. If avoiding school fees is the goal, the Studio is the only plan that does it.

What permit ready covers, and what you still provide

In short: The city drew the building; you supply the site plan, energy calcs, WQMP, soils report over 500 sq ft, and you cannot alter the plans without losing the fast track.

People search for pre approved ADU plans Temecula might offer, but the city never uses that phrase. Its term is Permit Ready, and the difference is practical. The city drew the house. You still have to draw the lot.

The Permit Ready ADU Handout says the plans take care of most of the design work, then adds that they need to be completed by the owner or a professional before submittal [2]. Completing them means supplying everything the architect could not know in advance. The site plan showing where the unit sits, its setbacks and its utility runs is drawn by the applicant [3]. The energy calculations (the Title 24 sheets) have to be updated for your orientation and your equipment [2]. The checklist includes a streamlined Water Quality Management Plan (WQMP) packet that you fill in for your drainage [2]. If the unit is over 500 sq ft, you also need a soils report from a California registered civil engineer, and a grading plan if more than 50 cubic yards of earth will move [2]. An electrical panel upgrade, common on older homes, takes its own permit [2].

Leave the plans alone while you do this. The handout warns that changing them, even moving a door, can make the project ineligible for the expedited process and can require your own structural calculations [2]. At that point you have a custom set that happens to look like the city's.

Who does the finishing work is up to you. The handout allows an owner builder to complete the plans, and it allows a professional [2]. A contractor handling ADU construction in Temecula needs an active state license and a City of Temecula business license to use the online permit account and pull the permits [2]. Either way, the finished set still goes through plan check. That timeline is next.

How the submittal works, step by step

In short: Six city steps, about three to four weeks of lead time before construction if nothing bounces.

The city lays out six steps, and the handout attaches lead times to most of them [2][3].

  1. Plan and research. Download the plan you want, read the Permit Ready ADU Handout, and confirm with Planning that your lot has no sensitive area or lot coverage problem [2]. Request an ADU address about 10 business days before you plan to submit [2].
  2. Design. Finish the set as described above, and work through the Permit Ready ADU Submittal Checklist (form PL-71a) line by line [9]. Register a Citizen Self Service (CSS) account about a week ahead, because every plan must be submitted digitally through that portal [2][9].
  3. Submit and pay. Upload the plans with the CD1 building permit application, the PL-75 ADU development tracking form, the hold harmless agreement, the ADU covenant, and the owner builder form if you are acting as one [3][9]. The covenant is recorded against the property, and it carries the city's rule that an ADU or JADU cannot be rented for short stays; Temecula does not allow short-term rentals in either [1][3]. The city runs a completeness check in about 24 business hours [2].
  4. City review. Plan review usually takes 7 to 10 business days [2]. Approval here does not mean you can pick up a permit.
  5. Clearances and permit fees. Before issuance you clear, as applicable, Building and Safety, Fire Prevention, Land Development, your water and sewer district (Eastern Municipal Water District or Rancho California Water District), Riverside County Environmental Health if you are on septic, the trash hauler, and TVUSD [2]. Then you pay the permit fees and the permit issues.
  6. Build and inspect. Inspections run from footings and setbacks through final [2]. A Release for Occupancy form closes the project after the last inspection passes [2].

Add it up and the paperwork alone runs about three to four weeks before a shovel moves, assuming nothing bounces back for corrections.

Lot conditions that can rule a PRADU out

In short: Setbacks under 5 ft, septic, pools, fire access, parking, HOA rules and the 50 percent or 1,200 sq ft cap.

The plans are fixed. Your lot is not. The handout lists the conditions that most often turn a Permit Ready ADU into a custom project, or add cost to it [2].

  • Setbacks. Temecula ADU setbacks for a PRADU are at least 4 ft at the side and rear, with the front set by zoning [2]. Anything under 5 ft may require special construction at the wall facing the property line, and that raises the price [2].
  • Size cap. The unit cannot exceed 50 percent of the existing home's floor area or 1,200 sq ft, whichever is less [4]. Small houses lose the two larger plans.
  • Septic. A septic layout can limit where the unit can go, and Riverside County Environmental Health has to confirm the system can carry it [1][2].
  • Fire access. A unit more than 150 ft from the road may need an access road [2]. Sprinklers are required only if the main house already has them [2].
  • Pools. A unit inside a pool barrier enclosure area triggers pool safety requirements [2].
  • HOA. Your association can impose design and site plan requirements the city does not [2].
  • Parking. The checklist asks you to show the required on-site space and to note whether the property is within half a mile of a transit stop, which waives it [9].
  • Planning checks. Sensitive areas and lot coverage are confirmed with the Planning Department before you submit [2]. Existing solar can affect an exemption depending on system size [2].

If two or more of these apply, price the custom route before you spend money finishing a city plan that may not fit.

City plans, builder plans, or custom plans

In short: City plans save the design fee, builder plans fold the site work into the job, custom plans fit lots the fixed layouts cannot.

A Permit Ready plan is one of three ways to get a buildable set. The right one depends on how well a fixed layout fits your lot and how much of the finishing work you want to carry yourself.

FactorCity Permit Ready ADU planBuilder planCustom plan
Design feeFree to download from the city [1]Varies by builder; some include their plans with a build contractPaid design and engineering
Who finishes the site specific workYou, or a professional you hire [2]Usually the builderYour designer and engineer
Changes to the layoutNot without losing the expedited path [2]Depends on the builderAnything the code allows
Fee positionSet by the size you pick (see the fee table above)Set by the size you pickSet by the size you draw
Plan check pathExpedited review, usually 7 to 10 business days [2]Standard ADU submittalStandard ADU submittal

Builder plans sit between the two. Woollard's ADU floor plans are free to homeowners who build with Woollard, and two of them, at 499 and 749 sq ft, match two of the city's plan sizes [13]. That makes the fee comparison direct: a 499 sq ft unit sits under both fee lines and a 749 sq ft unit sits under the impact fee line whichever set of drawings it comes from. What changes is who handles the site plan, the energy calculations, the soils report and the clearances. On a city plan that is you unless you hire it out. On a builder plan it is usually built into the job.

Go custom when the lot forces it: tight setbacks, a septic field in the wrong place, a slope, or a layout need none of the fixed plans meet.

What a PRADU still costs to build

In short: The plan is free; construction at the matching sizes runs about $225,000 at 499 sq ft and $290,000 at 749 sq ft on Woollard's published figures, plus fees.

The city is careful to say that the plans are free and the fees are not [1]. It does not publish a construction cost, because the city does not build the unit. The plan sheets save you the design fee and a chunk of plan check time. Every other line in the budget is still there.

For a sense of scale, Woollard's published Temecula figures at the two matching sizes are about $225,000 for a 499 sq ft one bedroom detached unit and about $290,000 for a 749 sq ft two bedroom detached unit [12]. Those numbers cover construction, plans, engineering, typical utility work and standard finishes [12]. City permit fees, school fees on units over 500 sq ft, and utility connection fees are added on top [12], which is exactly the fee layer the table earlier in this article walks through. At 749 sq ft that means roughly $4,030 in TVUSD fees before the permit issues; at 499 sq ft it means none. Detached units in the Temecula Valley generally run $390 to $450 per sq ft [12], and the full breakdown of ADU costs in Temecula covers garage conversions, attached units and junior ADUs as well.

Before you finish any set of drawings, city or otherwise, have someone walk the lot. Setbacks, septic, panel capacity and grading decide whether a fixed plan fits, and a site visit answers that in an afternoon.

Frequently Asked Questions

In short: Short answers to the questions Temecula homeowners ask most about the Permit Ready ADU plans.

What is the Temecula PRADU program?

The Permit Ready Accessory Dwelling Unit (PRADU) program is the City of Temecula's set of five pre-designed detached ADU plans, from a 499 sq ft studio to a 1,194 sq ft three bedroom, published free as PDFs on the city's ADU page [1]. The design work is done and pre-reviewed. Fees for submitting and building the unit still apply [1].

Are Temecula's permit ready ADU plans free of charge?

The plan sets are free to download [1]. The permit is not. You still pay building permit and plan check fees on every plan, Temecula Valley Unified School District fees on any plan over 500 sq ft, and development impact fees on the two plans over 749 sq ft [2][6].

Which PRADU plan is exempt from fees?

Only the 499 sq ft Studio avoids both development impact fees and school fees [2][6]. The 625 and 749 sq ft plans are exempt from impact fees but owe TVUSD fees at $5.38 per sq ft [2][6]. The 909 and 1,194 sq ft plans owe both. Permit fees apply to all five [2].

Can I modify a Permit Ready ADU plan?

You can, but the city's handout warns that changes such as moving a door can make the project ineligible for the expedited process and can require your own structural calculations [2]. At that point the set is reviewed as a custom ADU.

How long does PRADU plan review take in Temecula?

The city checks a submittal for completeness in about 24 business hours, and plan review usually takes 7 to 10 business days [2]. Approval is not issuance. The permit issues only after the agency clearances are in and the fees are paid [2].

Do I need a contractor for a Permit Ready ADU?

No. The handout allows an owner builder to complete and submit the plans [2]. If you hire a contractor, the city requires an active state license and a City of Temecula business license before they can use the online permit account and pull permits [2].

What changes for ADU impact fees on January 1, 2027?

Senate Bill 1117, signed September 29, 2026, takes effect January 1, 2027 [8]. For up to two ADUs on a lot, impact fees on a unit over 750 sq ft are calculated only on the square footage above 750, instead of the whole unit [5][8]. The 909 sq ft plan is assessed on 159 sq ft and the 1,194 sq ft plan on 444 sq ft. Plans of 749 sq ft or less were already exempt.

Can I rent a Temecula PRADU short term?

No. The City of Temecula does not allow short-term rentals in ADUs or JADUs, and the recorded covenant carries that condition [1][3].

Definition Bank

TermMeaning
Accessory dwelling unit (ADU)A self-contained second home on the same lot as a primary residence, with its own kitchen, bath and entrance.
Permit Ready ADU (PRADU)A city-drawn, pre-reviewed ADU plan set offered free by the City of Temecula.
Development impact feeA one-time city fee on new construction to fund roads, parks and facilities.
School fee (developer fee)A per square foot fee a school district charges on new residential space over 500 sq ft under Education Code 17620.
Certificate of ComplianceThe TVUSD document confirming school fees were paid or exempted, required before the city issues the permit.
Plan checkThe city's review of construction drawings for code compliance before a permit issues.
Citizen Self Service (CSS) portalTemecula's online system for submitting plans and permit applications.
Title 24 energy calculationsCalifornia's energy code worksheets showing the unit meets efficiency standards.
Water Quality Management Plan (WQMP)The stormwater and drainage packet required with a Temecula submittal.
Owner builderA property owner who pulls the permit and acts as their own contractor.

Entity Cards

City of Temecula PRADU program

PropertyValue
Administered byBuilding and Safety Division, Community Development Department
Plans5 detached plan sets, 499 to 1,194 sq ft
Governing handoutCD-70, Rev. July 20, 2023
ChecklistPL-71a, Rev. April 5, 2023
SubmittalDigital, through the CSS portal
Plan reviewUsually 7 to 10 business days

TVUSD developer fees

PropertyValue
Rate$5.38 per sq ft on residential space and ADUs over 500 sq ft
ExemptADU or JADU of 500 sq ft or less, exemption application required
EffectiveJune 16, 2026
OutputCertificate of Compliance, valid 30 days

SB 1117 (Cervantes)

PropertyValue
SignedSeptember 29, 2026
Chapter809, Statutes of 2026
EffectiveJanuary 1, 2027
EffectADU impact fees above 750 sq ft charged only on the excess, up to two ADUs per lot
AmendsGovernment Code 66311.5

Sources

  1. City of Temecula. Accessory Dwelling Units (ADUs) and Junior Accessory Dwelling Units (JADUs), Permit Ready ADU plan list (accessed November 6, 2026)
  2. City of Temecula Building and Safety Division. Permit Ready ADU Handout, form CD-70 (Rev. July 20, 2023)
  3. City of Temecula Community Development Department. Permit Ready ADU Workshop Presentation (February 22, 2023)
  4. City of Temecula Planning Division. Accessory Dwelling Unit handout and application, form PL-73 (Rev. January 29, 2026)
  5. California State Assembly, Committee on Local Government. Analysis of SB 1117 (Cervantes), existing law on ADU impact fees under Government Code Section 66311.5 (July 1, 2026)
  6. Temecula Valley Unified School District. Developer Fees, rates effective June 16, 2026 (accessed November 6, 2026)
  7. Lozano Smith. SB 543 Clarifies Accessory Dwelling Unit Limitations for School Impact Fees (2025)
  8. Best Best and Krieger LLP. California Further Expands State Accessory Dwelling Unit Law, AB 956 and SB 1117 signed September 29, 2026 (October 22, 2026)
  9. City of Temecula Building and Safety Division. Permit Ready ADU Submittal Checklist, form PL-71a (Rev. April 5, 2023)
  10. City of Temecula. Permit Ready ADU plan set, Studio 499 sq ft, title sheet TS0 (accessed November 6, 2026)
  11. CalMatters Digital Democracy. SB 543 Accessory dwelling units and junior accessory dwelling units, Chapter 520, Statutes of 2025 (chaptered October 10, 2025)
  12. Woollard Construction. How Much Does an ADU Cost in Temecula, CA? (accessed November 6, 2026)
  13. Woollard Construction. ADU Floor Plans Temecula, CA (accessed November 6, 2026)

Spencer Woollard

Spencer Woollard has 30+ years of experience in custom construction in Southern California. With over 350 completed projects including ADUs and bathroom remodels, Spencer is a trusted local contractor in Temecula, CA.

FREE CONSULTATION

Get a free consultation.

We will walk your property, tell you what fits, and give you a real number. Call (951) 551-6165 or request a site visit online.

HoursMon to Fri 7am to 5pm, Sat 8am to 1pm
Free · No Obligation

Request a site visit

Service
Contact
Address